Note that this is an optical scan of a hard copy and may contain
formatting errors.
ENVIRONMENTAL PROTECTION PLAN
Surface Coal Mine and Reclamation Project Point Aconi,
Nova Scotia
Prepared For: Pioneer Coal Limited
Submitted To:
Nova Scotia Department of Environment and Labour
Prepared by: Conestaga-Rovers & Associates
MAY 2006
R>~l:. NO 850090A (1)
31 Gloster court Dartmouth, Nova Scotia Canada 13313
1X9 Telephone: 502.468.1248 Facsimile: 902.468.2207
TABLE OF CONTENTS
PaZe
1.0 INTRODUCTION ............................
................................................................................1
2.0 iVlitigative
Measures........................................................................................................2
2.1 Groundwater
....................................................................................................................
2
2.2 Surface Water
...................................................................................................................
3
2.3 Terrestrial Resources
.....:.................................................................................................
4
2.4 Air Quality and
Dust.......................................................................................................5
2.5 Noise
..................................................................................................................................
6 2.6
VisualImpact....................................................................................................................7
3.0 Monitoring
........................................................................................................................
8 3.1
Baseline.........................,....................................................................................................8
3.2 Development and
Operation........................................................................................10
3.3 Post
Reclamation............................................................................................................12
4.0 Contingency
plan...........................................................................................................14
4.1
Spills.................................................................................................................................14
4.2 Groundwater
drawdocvn................................................................,.............................14
4.3 Surface Water Control System
Failure.............................,..........................................16
4.4 Acid Rock
Drainage.......................................................................................................
lb
4.5 Contaminated
Material.................................................................................................17
4.6 Fire
...................................................................................................................................17
4.7 Response when facility not
staffed..............................................................................17
4.8 Species at Risk
..................................................................................................._............17
LIST OF FIGURES
Figure 1-1 Site Location
Figure 1-2 Existing Site Features
Figure 3-1 Environmental Monitoring Locations
Figure 4-1 Water Supply Policy Boundaries
LIST OF APPENDICES
Appendix A Baseline Environmental Monitoring Data
Appendix B Contingency Plans
Appendix C Emergency Preparedness Policy
Appendix D Emergency Contact List
Appendix E Safe Work Practices
1.0 INTRODUCTION
This document forms the Surface Coal Mine and
Reclamation Project - Prince Mine Site Environmental Protection Plan (EPP). The
environmental assessment process has demonstrated that all significant negative
effects of the undertaking can be mitigated if the project is well designed and
implemented. It is the objective of the EPP to present a detailed plan for
development, operation and final reclamation of the surface coal mine such that
there are no significant adverse environmental or socio-economic effects.
All mitigation, monitoring and contingency plans are
included in the EPP. The mitigation section provides information on how to
lessen impacts. The monitoring section provides specific information on the
programs. The contingency program section provides information on what to do in
situations where action is required. The mitigation and monitoring focuses on
groundwater, surface water, terrestrial resources, air quality and dust, noise
and visual impact. Contingency planning presents detailed processes and
procedures in the event of an accident or unforeseen impact. This EPP addresses
many of the conditions of approval of this undertaking (as per the Terms and
Conditions for Environmental Assessment Approval by NSEL dated December 28,
2006).
Many of these plans were included in the environmental
assessment registration document and addendum; however, they are presented here
to reinforce commitments to environmental protection made by Pioneer Coal
Limited (Pioneer Coal). In many cases, these initial monitoring, mitigation, and
contingency plans have been revised to reflect:
- Detailed engineering design of mine development and
operation;
- Additional environmental baseline data collection
and analysis; - Comments and advice of the Community Liaison Committee (CLC);
and,
- Review comments provided by Nova Scotia Department of
Environment and Labour (NSEL).
While the EPP acts as a support document to the
Industrial Approval Application, it also consolidates environmental protection
plans for site operators, as well as regulators and other interested parties. As
such, this document should be retained on site at all times. The specific
contingency plans, contact lists and policies will also be posted on site for
quick reference.
asccsai+i
CONESTOGA-RCVERS & ASSCCIATE5
2.0 MITIGATNE MEASURES
The proposed mitigative measures are presented below
with respect to groundwater, surface water, terrestrial resources, air quality
and dust, noise and visual impact. Many of these mitigations protect more than
one of these valued resources. These are presented for guidance; however,
Pioneer Coal will modify mitigative measures to achieve regulated objectives, as
required, in consultation with NSEL and where applicable, the CLC. The
monitoring plan, as presented in Section 3, will provide a feedback loop to
Pioneer Coal to assess the effectiveness of mitigative measures. Pioneer Coal
will continually evaluate the mitigative measures and modify approaches as
required (i.e., effect of environment on the project) to ensure no significant
adverse impact on the environment.
2.1 GROUNDWATER
Groundwater issues at the site that may require
mitigation have been identified to include potential effects to surface water
from groundwater drawdown, groundwater control within the mine area and
groundwater use for domestic wells. Baseline and operational monitoring as
discussed in Section 3 will provide early warning of any unexpected changes
during mine development and operation such that mitigative measures can be
implemented to protect groundwater and surface water resources.
Mitigative measures where groundwater drawdown is
creating surface water effects may include:
- Changes to the dewatering program; and,
- Changes to the site drainage controls.
Control of groundwater is not anticipated as an
unmanageable issue at the site. Ample storage capacity is available within
existing underground workings, active pits and within the settling pond system
to hold and address groundwater entering the surface mine workings. Groundwater
entering the mine area will be directed to the portal and then into the
underground workings as described in the environmental assessment registration
document.
9_:0OrJ(', i5;
2
CChESTOCA-RCVERS & ASSOCIATES
Mitigative measures where groundwater effects to
domestic users occur are limited but may include:
- Changes to the dewatering program; and,
- Changes to site drainage controls in the case of
dug wells.
It should be noted that due to the limited mitigative
options, a comprehensive Contingency Plan has been developed for this aspect of
the project, including a Water Supply Policy (see Section 4.2).
2.2 SURFACE WATER
It is inevitable in a site of this nature, with active
waste piles and earth moving activity, that there will be some erosion of
exposed surfaces leading to high sediment levels in the runoff. The operator
will make every effort to minimize the area subject to erosion.
Measures that will be applied include the following:
- Design and construction of waste piles with
material placed in lifts; side slopes will be progressively vegetated where
required;
- Progressive reclamation will occur
as part of ongoing operations;
- All areas contoured to their final grade will be
fertilized and seeded to promote rapid reestablishment of permanent vegetation;
- Temporarily inactive areas subject to erosion will
be stabilized with mulch, or geotextiles as required;
- Clean surface water will be diverted away from
active mining area via existing land contours and constructed berms to minimize
the volumes to be handled;
- Sediment traps will be constructed to slow erosional
surface flows and reduce the volume of sediment reaching the main treatment
ponds;
-- All channels for the drainage control system will
be stabilized with geotextile and rock; and,
- Work will be completed in accordance with
legislation and standards, including the NSDEL Erosion and Sediment Control
Handbook for Construction Sites and Environment Canada's Key Elements of an
Erosion and Sedimentation Prevention and Control Strategy.
ea;:^;s.~ rt;
3 CONESTOGA-ROVERS & ASSOCIATES
Management of surface water and water within the
existing underground workings are essential elements in mitigating significant
impacts to the receiving systems. The approach to surface water management is
described in detail in the IA Application Supporting Document (Section 4). In
summary, all water that has come into contact with the active mine, including
groundwater, will enter the workings until capacity is reached. After that,
water will be managed through the existing treatment pond system eventually
discharging into the watercourse leading to Morrison Brook.
The treatment pond configuration consists of a series
of three ponds providing for batch treatment using flocculants, if required. Use
of coagulant is expected to be minimal. The existing discharge location and
structure will be used. The use of a sump as a primary settling pond within the
active pits prior to pumping to the existing settling ponds allows for
additional settling of sediment.
As described in the IA Application Supporting Document,
acid rock drainage (ARD) is not expected to be an issue. Testing has occurred
and will be ongoing. The ERD outlined testing to date and the fact that most
materials are net acid consuming. Contingency plans if ARD is encountered are
presented in Section 4.4 of this EPP, and in Appendix A.
2.3 TERRESTRIAL RESOURCES
Mitigation measures to disturbance of wildlife habitat
include:
- Scheduling clearing activities to occur outside the
nesting period (at this location prior to early April is preferred);
- If ground nests are encountered, establish
exclusion zone around nest during the breeding season;
- If cavitv nests encountered, delay cutting until
after nesting season; and,
- Implement measures in consultation with NSDNR or
Canadian Wildlife Service (CWS) when needed.
Generalized measures to reduce disturbance of
terrestrial habitat and species could include:
- No wildlife harassment policy, limit use of ATVs;
- Scheduling to avoid sensitive periods;
-- Modifications to activities;
50o90;')
4 CONESTOOA-ROVERS & ASSOCfATES
- Limiting clearing/ disturbed
area at any given time;
- Avoid mechanical clearing and establish exclusion
zones around bird ground nests during the breeding season;
- Flagging of areas to be cleared in advance;
- Maintenance of buffer zones from watercourses
(permanent or intermittent) ;
- Topsoil stockpiling where sufficient material is
present and reuse in reclamation;
- Sediment and erosion control plan including
stabilization of open areas and appropriate drainage control;
- Dust control measures to reduce adverse impacts on
plant and animal health;
-- Waste management - removal of human waste, proper
storage and removal of domestic garbage;
- Blasting to meet DFO guidelines near fish habitat;
- Petroleum, oil and lubricant (POL) handling
procedures; and, - Contingency planning.
Although bat hibernating areas are not known for the
mining area, if bats or long-eared owls are encountered during site activity,
Pioneer Coal will contact NSDNR Wildlife Division and take appropriate
mitigative action as directed.
Although Long Eared Owl nests are not anticipated
within the site area, if any raptor nests are encountered, NSDNR guidelines
(Bald Eagle, Osprey, Colonial Birds, such as herons and cormorants and Woodland
Hawk) will be followed.
2.4 AIR QUALITY AND DUST
Dust control requires careful and consistently applied
mitigative measures throughout the project, if non-compliant or nuisance levels
are to be avoided. Pioneer Coal may vary the mitigations depending on specifics
of the situation so long as the dust levels are in accordance with the
regulations. ti-litigative measures that are part of overall operations plan are
as follows.
Mining Operations:
The control of fugitive dust from the mining operations must center on provision
of moisture control measures, such as spraying with water as required.
Operations based in relatively deep pits will not generally have much direct
offsite impact but could contribute to general dust levels at critical times if
not controlled.
s5wse ( 1)
5 CcNESrocA-ROVERS &
ASSOCtaTEs
On-site Vehicle Operations: To
minimize dust produced by on-site vehicle operations, the following may be used
as required:
- Wet suppression controls on unpaved surfaces;
- Hardened surfaces where practical;
- Speed reduction; and,
- Use of large haul vehicles so as to minimize trip
frequency.
Waste Rock Conveyor:
The use of a belt conveyor to transport the waste rock from the pit to the waste
rock pile can provide benefits in the control of dust levels on the site.
The conveyor system will be used when it is feasible,
given logistics of the site. Material on the conveyor will be kept moistened by
the use of sprays, where required, so that wind entrainment will be minimized.
Waste Piles Surface Stabilization: Wind erosion from
elevated waste piles containing finely divided material can be a major source of
dust at mine sites. Slopes may be stabilized with mulching and / or vegetation,
where appropriate.
Off-Site Transportation:
The tractor trailers will be fitted with tarp covers to
minimize dust emissions and spillage. To eliminate the tracking of site
materials on local roads, the coal transport trucks will be washed as necessary.
Pioneer Coal is aware that the proposed project will be
regulated by the Nova Scotia Air Quality Regulations and will ensure that
operations meet these requirements.
2.5 NOISE
The proposed mitigation measures for noise are outlined
as follows:
- The majority of operations will occur in the pit
well below ground surface, thereby, providing excellent noise shielding; and,
- Noise from the equipment and lack of effective
mufflers is a source of noise. Regular maintenance of the equipment will reduce
noise levels.
6 CCNESTOGA-ROVERS & AS5oC(ATES
This combination of measures will adequately mitigate
potential noise impacts. Ongoing feedback from the community via the CLC will
assist Pioneer Coal in operating procedures to minimize impact of noise on the
residents.
The mitigation procedures may vary as long as noise
levels are in accordance with the regulatory approval.
2.6 VISUAL IMPACT
A visual impact assessment has been completed and
provides information to assist in the mitigation of certain visual impacts.
General mitigative measures for reducing visual impacts
may include:
- Locating stockpiles to minimize visibility;
-- Reducing height of stockpiles in key locations;
-- Orientating stockpiles to minimize visibility;
- Maintaining key buffer zones; and,
- Planting of, or vegetation management to encourage
certain species in key viewplanes to minimize visibility.
Specific results of the viewplane assessment are
summarized in Table 9-1 in the lA Application Supporting Document with
additional information on the viewplane assessment.
As outlined in the IA Application Supporting Document,
a number of the viewplanes that had negative impacts have been or will be
mitigated. All of the stockpiles will be returned to the excavated area by the
end of the project as well thus eliminating residual visual impacts once fully
vegetated.
The nature of visual impacts is subjective and ever
changing thereby making continual input important. Pioneer Coal
will continually work to minimize visual impact and seek
to have input from the CLC on an ongoing basis. Where possible, mine development
and operation will minimize impact on both residents and visitors to the
community; however, some short term residual impact to aesthetics is expected to
remain at certain vantage points.
55CC9C(t)
7
CONESTCGA-RCVERS 8c ASSOCIATES
3.0 MONITORING
The monitoring program for groundwater, surface water,
dust and noise are discussed in the following sub-sections in terms of baseline,
operation and postreclamation monitoring.
3.1 BASELINE
Groundwater
Baseline groundwater quality and water levels for the
site are well understood from environmental site assessment activities and
existing data from nearby sites. This information will be supplemented through
the establishment of three nested monitor well locations (GW1-3) as detailed
below, the use of up to two "willing host" domestic wells at locations where the
homeowner is hooked to the municipal supply, the NSEL Observation Well at Point
Aconi and the NSP Observation Well M-15 for which Pioneer has obtained
permission to obtain data. These wells will provide adequate coverage to detail
any possible changes in water quality of levels through the baseline,
operational and post-reclamation phases.
Water level monitoring on a weekly basis for year one
is proposed, as well as water quality sampling for general chemistry on a
monthly basis.
(D C Location { Rationale
Wti7 ~ Down-gradient from site - one well
completed ~ To monitor possible water level and chemistry
in surHcial materials changes
from site activities
` Up-gradient from site - nested well with one To
monitor possible danges to water levels and
GW2 I completed in surficial materials at top
of chemistry from up-gradient sources and water
~bedrock- and one completed in
bedrock levels from site activities dewatering) -_
t Between site and Morrison Brook - one well
Gi-Y'3 ~ completed in surficial materials at top of bedrock
To monitor possible changes to water levels and
chemistry from site activities to i?-4orrison Brix)k area
Domestic Well Nl ~ Cross-gradient from site in area. of
former ; To monitor possible water level and chemistry domestic
wells hooked to municipal system changes from site
activities
Domestic Well #2 D°+'m"gradient from site in area of
abundant To monitor possible water level and chemistry
domestic wells changes from
site activities
To monitor possible water level and chemistry
\SFL o$S ~ Up-gradient from
site changes from site activities and continue baseline
data set from N5EL Down-gradient from site in area of abundant To nuonitor
regional water level changes
domestic wells ,
NSI' OBS (41-15)
Surface Water
Baseline surface water monitoring stations will be
established at three locations chosen to assess the condition of surface water
entering and exiting the site to
asc;o90 i;y 8 CONESTOGa-ROVERS
& ASSOCLATES
determine pre-development site influences to the
surrounding environment. Compliance locations (3) for the proposed monitoring
are shown on Figure 3-1. The table below outlines the locations and rationale
for the surface water sampling stations.
Location
Rationale
5W1
SYV2
Coal Hollow Brook, downstream from Point
Aconi Road [ downstream frorn potential site
influence
To assess the condition of Coal
Hollow Brook
MacDcmald Brook, upstream from confluence with Morrison
Brook
To assess surface water from water treatment ponds
leaving the site via MacDonald Brook - only when - effluent is leaving ponds
To assess the condition of 1lorrison Brook downstream
from potential site influence
h9orrison Brook, downstream from confluence
SW3 ~ with lvtacDonald Brook, upstream of Sheri Lee
Lane/ Millpond Road
Samples from all of the surface water points will be
submitted monthly for chemical analysis for general chemistry, metals and total
suspended solids (TSS). Flow monitoring will be completed at all locations at
the same frequency. Note that seasonal conditions (ice) and safety
considerations (floods) may make some stations periodically unavailable.
Dust
Baseline sampling was completed for suspended
particulate. Baseline suspended particulate (i.e., those not generated from
surface coal mining activity) in the immediate vicinity of the site may include:
- Local vehicular traffic (cars, light trucks, school
buses, garbage trucks, etc.);
- Traffic along Highway 162 (much associated with
NSPI Point Aconi Generating Station); and,
- NSPI Point Aconi Generating Station.
The location selected is adjacent a residence at the
end of Forrest Lane (P1D No. 15298466) as approximately shown on Figure 3-l.
Samples were taken on March 6, 2006 and March 13, 20Q6. The results (as shown in
Appendix A) are 13.4 lZg/m3 and 6.6
ltg f m3, respectively.
NSBL limits for total suspended particulate (TSP) are
as follows:
Annual Geometric Mean 70 pg/M3
Daily Average (24 hr) 120 }zg/m3
a:,caae ~•; 9 CGNESTOGA-ROVERS
& A5SOCiATES
Noise
The baseline noise emissions (i.e., those not generated
from surface coal mining activity) in the immediate vicinity of the site may
include:
- iVTSPI Point Aconi Generating Station;
- Marine activity (e.g., boating) and water action
(e.g., waves);
- Local vehicular traffic (cars, light trucks, school
buses, pick-up/delivery, etc.);
- Traffic along Highway 162 (much associated with
NSPI Point Aconi Generating Station).
The locations for baseline sampling were selected near
Prince Mine Road and site entrance as shown on Figure 3-1. The first monitoring
interval was from 24/03/2006 at 4:OOPlvf
to Ol/04/2006 at 11:15PM (as completed for N1). Raw data is provided in Appendix
A.
Peak Level: 112.5 dB, 24/03/20E}6 4:00:45PM
Max Level: 86.8 dB, 28/03/2006 7:20:23AM
Min Level: 31.6 dB, 25/03/2006 10:20:44AM
NSE[. limits for sound levels are as follows:
Leq 65 dBA 0700 -1900 hours (days)
60 dBA 1900 - 2300 hours (evenings)
55 dBA 2,300 - 0700 hours (nights)
3.2 DEVELOPMENT
AND OPERATION
All project activities will be monitored by the
company's supervisory personnel. As well, the ongoing environmental monitoring
provides continual feedback on the operations and their impact to the
environment. The numerical results of the environmental monitoring (dust, noise,
surface water, and groundwater) are augmented by visual assessment and community
liaison. The operation is continually changing as environmental (e.g., weather)
and operational conditions vary. As part of operations, regular inspections of
the site are made by Pioneer Coal supervisory personnel, as well as the
quantitative monitoring plan discussed in this section. It is a dual goal of
Pioneer Coal to complete the Surface Coal Mine and Reclamation Project and
minimize negative impact on surrounding environment and community.
860090 (i )
10 CONESTOGA-ROVERS &
AssdcwrEs
Groundwater
The baseline data set will be augmented through the
development and operations phase and provide a comprehensive data set for
comparison and evaluating trends. For the first year of site work, weekly water
level monitoring and monthly sampling with analysis for general chemistry is
proposed. The water level monitoring should be monthly after the first year of
site work and the water quality sampling completed on a quarterly basis after
year one of site work. Should any major variations occur in the water levels or
water quality, increased frequency of
monitoring may be required.
Surface Water
Baseline surface water monitoring stations will be used
to the greatest extent for monitoring to continue the data set for comparison
and evaluating trends during the development and operational phases of the
project. Surface water monitoring will continue on a monthly basis sampling for
general chemistry, metals and TSS. Flow monitoring at the established surface
water monitoring stations will occur monthly throughout the development and
operational phase of the project.
Monitoring of water levels within the Prince Mine
workings will be ongoing during all site work. The frequency will vary depending
on environmental and operational factors, as well as results
of monitoring (i.e., rate of change). NSEL will be kept
apprised of the water level changes and the anticipated management plan. A
discussion of water levels within the Prince Mine is presented in Section 4 of
the IA Application Supporting Document.
Dust
Dust monitoring will be conducted over a twenty-four
hour period every sixth operating day. The results will be submitted to the
regulators as directed by NSEL.
The results will be assessed in terms of baseline
suspended particulate data, maximum allowable concentration, and to assist in
assessing efficiency of mitigative measures.
The proposed monitoring location is shown an Figure
3-1. One location is proposed. Baseline monitoring was completed to allow a
benchmark of comparison for operating data.
11 CONES70GA-ROVERS & AS50CIATES
Noise
Noise monitoring will be
conducted over a minimum of two hour period each operating day during daytime
(0700 hours to 1900 hours) and nighttime (1900 hours to 0700 hours). The results
will be submitted to regulators as directed by NSEL.
The results will be assessed in terms of baseline
suspended particulate data, maximum allowable concentration, and to assist in
assessing efficiency of mitigative measures.
The proposed monitoring locations are shown
on Figure 3-l. Two locations are proposed. Monitoring
includes instantaneous noises, as well as average dBA levels.
Baseline monitoring was completed at these stations
prior to commencement of operations to allow a benchmark of comparison for
operating data.
3.3 POST RECLAMATION
The reclamation plan is discussed in Section 11 of the
IA Application Supporting Document. Reclamation involves removal of site
infrastructure (with the exception of the CBDC Mechanical Shop and existing
water treatment ponds and related building), final grading / shaping,
compensating wetland habitat and revegetating the site.
Long-term monitoring will likely include monitoring of
success of constructed habitat (both terrestrial and aquatic). Surface water
monitoring of quality and quantity will also be completed as reclamation
directly involves surface water. Groundwater monitoring will occur to assess
stabilization of water levels. The specific type, frequency and follow up
required post reclamation will be discussed with regulatory authorities and CLC
at the time that final reclamation is being undertaken. In part, the results of
ongoing monitoring during mine operation influence the design of the long-term
monitoring program.
Reclamation plans should include site monitoring, and
schedules, by the proponent for the following:
- Monitor progress of revegetated areas following
initial planting until vegetation is successfully established;
860,090 (1)
12 CONESTOGA-ROVERS & ASSOCIATES
- Regularly conduct soil analyses for nutrients and
pH until vegetation is demonstrated to be successfully established;
- Take corrective action in areas showing evidence of
erosion, sedimentation or slope failure;
- Take appropriate measures to address evidence of
excessive vegetation stress, invasive species or poorly established areas; and,
- A longer term monitoring schedule to determine any
necessary site restoration repairs, and to review progress toward development of
a self sustaining ecosystem.
The re-establishment of wetlands in the footprint of
the mine is an important element of the overall reclamation of the site.
Approximately 10 ha of wetlands are being disturbed due to the mining activities
and it is important to replace these wetlands within the same general area. A
detailed plan is provided in the IA Application Supporting Document based on the
underlying principle of "no net loss" of wetland function that shows a
reclamation plan that shows approximately 13ha of wetland habitat.
13 COhESTOGk-ROVERS & ASSOCIATES
4.0 CONTINGENCY PLAN
The purpose of the section is to provide for review and
approval a contingency plan that addresses accidental occurrences including, but
not limited to:
- Spills;
- Groundwater drawdown;
- Surface water control structure failure;
- Acid rock drainage;
- Contaminated material; - Fire;
- Procedures for responding to incidents occurring
during times when the facility is not staffed (e.g. evenings, weekends,
holidays); and, - Encountering species at risk.
Specific Contingency Plans for Site Contingency and
Spill Contingency are provided in Appendix B and the Dispute Arbitration Process
and Policy.
4.1 SPILLS
Site specific Hazard Assessments and Inspections will
be completed on site at regular intervals, in accordance with Pioneer Coal's
Company Safety Manual. Proper storage of materials along with an organized and
tidy workplace is promoted as the first step in the prevention of spills.
The Spill Contingency Plan in Appendix B provides
additional detail.
4.2 GROUNDWATER DRAWDOWN
Groundwater drawdown will be mitigated as outlined in
Section 2 and monitored as previously outlined in Section 3. There are two
possible types of groundwater drativdown that need to be addressed by the
Contingency Plan:
1. Groundwater drawdown in areas where no domestic
wells occur but where surface water may be affected; and,
2. Areas where domestic wells may be affected.
For areas where there are no domestic wells,
groundwater levels or water quality mav affect local surface water quality. The
monitoring program will identify any areas where this is occurring and the
mitigation will address issues.
asccso (s )
14 CGNESTGGA-ROVERS & ASSOCIATES
Far areas where groundwater use for domestic purposes
occurs, there is a need for a contingency plan. Groundwater use in the area for
domestic use occurs for some of the residences. Pioneer proposes a Water Supply
Policy as outlined below for domestic wells within 800 metres of the site to the
south and up to the Brogan Surface Mine limits to the north. "The geographic
area that the Water Supply Policy applies to is outlined on Figure 4-1.
Water Supply Policy
Complaints of loss of Quantity or quality of water in a
well may be directed to Pioneer Coal's local manager during operating hours 0700
to 2300 hours in person or by telephone on a 24 hour basis.
While emergency matters can be reported verbally, when
time permits, a written summary can be helpful to all parties and is preferable
and will need to be prepared.
Upon receipt of the complaint within the area described
above, Pioneer Coal will supply potable water and begin discussions with the
property owner on a remedy. As part of the actions to be undertaken by Pioneer
Coal, the company will arrange and pay for an independent third party to
investigate the matter promptly. The resident will be advised in writing of the
results of the investigation and provided a copy of all relevant information
from the investigation such as water chemistry results.
If the loss of water quantity or quality is the fault
of the company, Pioneer Coal will:
a) continue to supply water to the residence until the
mater has been resolved;
b) agree in writing with the resident on a mutually
acceptable arrangement;
c) in the event that a mutually agreeable arrangement
cannot be concluded, then an independent arbitrator, agreeable to both parties,
will be appointed to review the matter and this/her decision will be binding,
without appeal, on both resident and Pioneer Coal; and,
d) if the resident and Pioneer Coal cannot agree on the
name of an arbitrator, then each will appoint another party as the third
arbitrator and as the Chairman of the Arbitration Board. The majority decision
of the Arbitration Board will be binding without appeal on both the resident and
Pioneer Coal.
e5iK-yo ;1 )
1 5 CONESTOGA-ROVERS &
AssociArEs
Should a complaint be received by the local manager for
a residence outside of the area identified on Figure 4-1, Pioneer Coal will
examine the situation on a case by case basis.
4.3 SURFACE WATER CONTROL SYSTEM FAILURE
In the event that an extreme storm event occurs or
other circumstances cause unintentional release of effluent from the site,
Pioneer Coal will divert its resources and engage other resources as necessary
to respond properly. Measures taken may include diversion of water into the
active pit area, installation of pumps and temporary works to mitigate impacts
and rehabilitation of adversely affected areas. Holding ponds and ditches are
constructed with adequate freeboard provision to prevent overtopping. Our
settlement pond system will be equipped with an emergency overflow pipe in the
event of an extreme occurrence. This emergency overflow prevents a possible
breaching of the ponds.
4.4 ACID ROCK DRAINAGE
Periodic testing of representative rock units will
confirm acid producing / consumption data for the site. Although acid rock
drainage (ARD) is not expected to be a problem at the mine site, continued
evaluation and monitoring will ensure that any problems will be quickly
identified. If mining results in ARD, lime can be added to the mine sump prior
to pumping the water to the settling ponds or at the influent point to the
settling ponds. Massive storage capacity exists within the pit areas for
wastewater. As a result, Pioneer Coal can utilize these areas for initial
monitoring and identify the problem at the source.
Prior to extraction of coal, samples will be taken and
analyzed according to approved acid consumption/ production test procedures. The
results of this testing program will be available to guide the operator and
regulator with respect to the potential for acid generation. Although the coal
and some of the adjacent strata may be acid generating the waste rock has excess
acid consumption capacity to neutralize the effect.
Areas where the coal is handled can be neutralized with
limestone or acid consuming rock to buffer the acid generation. The drainage
from the active pit areas, and any other location where coal is located, will be
controlled arid
8-', 00"0 11 )
16 CorrESrocA-ROVERS
& AssocwrEs
directed to the settling ponds for pH control if
necessary. The drainage will be tested for acidity before being discharged to
the treatment system.
The Contingency Plan in Appendix B provides additional
detail.
4.5 CONTAMINATED MATERIAL
If contaminated material is encountered on site, the
material will be collected and transported from the site and disposed of at an
appropriate facility. An area impacted by petroleum hydrocarbons (less than 25m3)
has been identified near the portal. This area of impacted soil will be properly
remediated during the course of the mining project according to N5DEL
requirements.
The Spill Contingency Plan in Appendix B provides
additional detail.
4.6 FIRE
Site specific Hazard Assessments and Inspections will
be completed on site at regular intervals in accordance with the Company Safety
Policy. An adequate number of fire extinguishers will be available for use on
site. The locations will be identified and employees will be trained in their
proper use. An Emergency Response Plan will be available on site.
4.7 RESPONSE WHEN FACILITY
NOT STAFFED
The site is proposed to be operational as a year round
operation with staff expected to be present 24 hours a day performing differing
functions. Responses to emergency situations while the site is not staffed would
be to use emergency response contact list outlined in Appendix D.
4.8 SPECIES AT RISK
Approaches to management of species at risk if
unexpectedly encountered include prioritization of avoidance. If avoidance is
not possible, mitigation measures will be implemented to minimize impact on the
population. Where loss is anticipated, this will be undertaken within the
context of maintaining the viability of the population and will be.~ conducted
in a manner contributing to the knowledge base of the species, its habitat, and
interaction with development, in order to further long-term survival of the
species.
bscego c " )
17 CONE5TOGa-RQVERS &
Associares
Regulatory Consultation - As part of environmental
protection planning, contingency planning and monitoring, the proponent will
work with regulatory agencies such as NSDNR, Wildlife Division for on-going
development of appropriate protection strategies and research initiatives where
necessary.
P Fouw c ; )
1$ CCNES70GA-ROVERS & ASSOC WTES